Jaipur Metro Phase 2 Civil Work Starts At Sitapura Depot

Jaipur Metro Phase 2 moved into visible execution on July 22 as groundwork and piling began at Sitapura depot for the 41 km Prahladpura-Todi Mod corridor.
Jaipur Metro Phase 2 Civil Work Starts At Sitapura Depot
By ILJC Team|

Jaipur Metro Phase 2 moved into a more visible execution stage on Wednesday, July 22, 2026, when groundwork and piling were ceremonially started at the Sitapura metro depot. The update matters because it shifts the project conversation away from approvals alone and toward on-site activity for the city's long-promised next metro corridor.

The broader project remains the same high-stakes mobility expansion already mapped for Jaipur: an approximately 41 km north-south corridor from Prahladpura to Todi Mod. But this release adds a more practical milestone by tying that larger plan to a specific depot-site construction start and to the first visible steps of civil work.

Quick Highlights

  • Groundwork and piling for Jaipur Metro Phase 2 were launched at the Sitapura metro depot on July 22, 2026.
  • The Phase 2 corridor is described as about 41 km from Prahladpura to Todi Mod.
  • The total project cost is pegged at more than Rs 13,037 crore.
  • The first package already has an LOA worth more than Rs 918 crore.
  • The route is meant to strengthen connections across Sitapura, VKIA, the airport, Tonk Road, SMS Hospital, the railway station, Ambabari and Vidhyadhar Nagar.
  • An underground station in the airport area is part of the plan.

Why this update matters more than another announcement

Jaipur has already seen major Phase 2 headlines this year around cabinet approval, cost estimates and package-level sanctioning. What makes this July 22 update different is that it is tied to a physical site and a specific construction activity. Once piling and depot-side work enter the story, the project starts looking less like a policy promise and more like an infrastructure programme with visible momentum.

That does not mean the full corridor is suddenly close to completion. It does mean the project has crossed another threshold in the long chain from approval to delivery, and that threshold usually matters more to commuters than ceremonial language alone.

Jaipur Metro Phase 2 itemCurrent detail
Current on-ground milestoneGroundwork and piling start at Sitapura depot
Full corridor lengthAbout 41 km
RoutePrahladpura to Todi Mod
Project costMore than Rs 13,037 crore
First package statusLOA above Rs 918 crore already issued
Special alignment featureUnderground airport-area station

What the corridor is expected to connect

The route has been positioned as a city-shaping corridor rather than a narrow extension. The release highlights its role in linking industrial and residential zones from Sitapura to VKIA, while also improving access to major destinations including the Jaipur Airport, Tonk Road, SMS Hospital and Stadium, the Collectorate, the railway station, Ambabari and Vidhyadhar Nagar.

That mix matters because it combines everyday commuter demand with institutional and transport-node traffic. A line that touches workplaces, hospital zones, airport movement and dense residential areas can change more than just travel time. It can alter how people plan work trips, hospital visits and cross-city movement across some of Jaipur's busiest belts.

What happened during the July 22 programme

The day was not limited to the depot ritual. Bhajan Lal Sharma also travelled by metro from Mansarovar to Chhoti Chaupar, reviewed the Phase 2 model, inspected the proposed Khasakothi interchange station site from the metro cockpit and later visited the art gallery at Chhoti Chaupar station.

Those details are politically visible, but the stronger infrastructure takeaway is that the government is now trying to present Phase 2 as both symbolic and active at the same time: a high-value long-term city project that has begun to show movement on the ground.

What to watch next

The next meaningful test is whether this depot-side start is followed by broader, sustained civil-work progress across the initial package rather than remaining a ceremonial marker. The first package already carries an LOA worth more than Rs 918 crore, so the key question is how quickly that paperwork converts into visible construction output.

Beyond that, Jaipur will be watching for pace on the wider corridor, clarity on later packages and whether the airport-linked underground component and interchange planning move forward without delay. If those pieces align, Phase 2 could begin turning from a long-promised metro upgrade into a genuinely city-shaping transport build.